Shoreland Subdivision Water Improvements, South Rollins Road, Phase 2

City Project No. 83521

This project consisted of replacing 4200 linear feet of pipelines originally installed in 1928. The residents on Winchester Drive, Corbitt Drive, Francisco Drive, Marin Drive, Oak Grove Avenue and surrounding areas will see improved water quality, fire flow and water pressure to their homes.

Scope
: The work consisted of installing new water mains in the City of Burlingame and San Mateo County. Approximately 1,010 linear feet of new 10-inch, 50 linear feet of new 8-inch, 3,100 linear feet of new 6-inch, and 60 linear feet of new 4-inch Polyvinyl Chloride (PVC) and Ductile Iron water main on Corbitt Drive, Francisco Drive, Marin Drive, Oak Grove Avenue, and Winchester Road. The existing 4-inch, 6-inch, and 8-inch water mains were abandoned in place. The construction method was a conventional open trench and the water main was typically installed at three to five feet depth of cover.