The City of Burlingame has approved an application for construction of a new five-story, 19-unit residential condominium building with at-grade parking at 128 Lorton Avenue (adjacent to the existing five-level public parking garage).

Planning Commission Meeting - June 12, 2023
At public hearing on June 12, 2023, the Planning Commission approved an application for Amendment to Design Review and Density Bonus Waivers/Modifications for changes to the previously approved project.   The staff report, attachments and plans are provided below.

Staff Report
Attachments
Project Plans

Planning Commission Action Meeting - July 13, 2020
The Planning Commission approved this application on July 13, 2020.   The staff report, attachments and proposed plans are provided below.

Staff Report
Attachments
CEQA Class 32 Infill Exemption
CEQA Class 32 Infill Exemption - Appendices

October 15, 2019 Planning Commission Study Meeting
The Planning Commission reviewed the application as a Design Review Study Item at its meeting on October 15, 2019.   The Commission took input and provided feedback on the design of the proposed project, but no action was taken at the meeting.  The application will return for action at a future date.  The staff report, attachments and proposed plans are provided below.

Staff Report
Attachments
Project Plans

Project Description
The following are pertinent details regarding the proposed development:

Zoning: R-4 (R-4 Incentive Overlay)
Site Area: 7,500 SF 
Proposed Units: 19 residential condominium units
Parking: 17 spaces (using vehicle lifts)
Building Height: 5 stories, 61'-1" to top of parapet (4 stories above at-grade garage)

Contacts

Project Planner
 
Ruben Hurin, Planning Manager
650-558-7250 
rhurin@burlingame.org 

Project Applicant of Record
Louisa Zee Kao
Murphy Wood, Inc.
Lzeekao@murphywood.com